The sensor that worked half the time
How one “loose cable” call became a supplier CAPA, and how each QES stage moved it forward. Read the strip below for the whole story in ten seconds; open any stage for the detail.
The lifecycle at a glance
Every QES event passes through the same five steps. Each step answers one question before the event moves on.
Why the first ticket matters
The first event was “solved” in a phone call. Whether it became a QES ticket decided whether anyone would ever see the pattern.
of field events like this one are never logged. They end as an email: “swapped the cable, all good.”
Email only pattern invisible
The second site looks like a brand-new problem. Three good cables get scrapped. Nobody connects the two events, and more faulty sensors keep shipping.
QES ticket pattern found
The second ticket lands next to the first. The QMS manager sees the same symptom twice and asks why the “failed” cables work everywhere else.
The setup in the field
Two cables, two connections. The symptom: the sensor does not connect to the device.
Stage by stage
Left: what happened in this example. Right: what QES holds at the end of the stage. The diamond is the decision that moves the event on.
Report
Support · Sales repWhat happened, where, and what did we try?
- Site A. Sales rep calls support: the sensor won’t connect. Support says swap the red cable. It works. Recorded as a cable issue and a QES ticket is raised.
- Site B, later. Same symptom. Swap cable: still no connection. Second cable: no. Third: no. Fourth: works.
- Three cables reported as failed, yet those cables work fine elsewhere. Support raises a second QES ticket.
In your work: raise the ticket even when the fix worked. A solved problem is still data.
Triage
QMS managerIs this a one-off or a pattern, and is it reportable?
- The QMS manager reviews incoming events and sees Tickets A and B side by side.
- Same symptom, same “fix”, at two sites. And “bad” cables that are not bad. Something is off, but it is not yet clear what.
- Reportability: not an adverse event, with the reason recorded. Nothing to report to the authorities; revisited if the investigation finds more.
- Suspected type: deviation. The cables don’t explain it, so something in the product or process is likely off.
In your work: look for repeats; two similar tickets are the strongest signal QES can give you. Decide reportability now: if it is a serious incident, the reporting clock is already running. Mark the type as suspected; Assign confirms it.
Investigate
QMS manager · EngineeringHow far does it go, how risky is it, and what is the root cause?
- Quick assessment: the problem is bigger than cables. Risk assessment judged not required, and that decision is documented with its reason.
- A test task is issued. Testing shows the sensor’s USB-C connector is badly soldered to the PCB. Plug the cable in one way: works. Flip it: fails.
- That is a 50/50 chance on every plug-in. It also explains Site B: each “new cable” was really a new coin toss. The fourth happened to go in the right way up.
- Engineering test SOPs reviewed. Root cause: insufficient solder paste on one side of the connector during chip install at the supplier.
In your work: “not required” is a valid answer only when the reason is written down. Then keep asking why until the answer is a process step you can change, not just a broken part.
Assign
QMS manager → Factory · Supplier · ProductionWhat do we change, and who owns each action?
- Type confirmed: deviation, matching the suspected type from triage. A deviation needs a full CAPA, so the CAPA is opened and each action gets an owner.
- Supplier: supplier issue raised to correct the solder paste process at chip install.
- Factory: replace the faulty sensors at the affected sites.
- Production: rewrite the production SOPs and add a cable-flip check to final test, and train the testers.
In your work: confirm the type before you assign; it decides the path. If it differs from triage, record why. Then give every action a name and a due date: an action without an owner is a wish.
Track & Outcome
QMS manager · ProductionIs each action done, and did it work?
- Each action is tracked while the fix is in progress, through to its outcome.
- Replacement sensors shipped to affected sites (luckily only a few units).
- Production SOPs rewritten. Final test now includes flipping the cable, so both orientations are checked; testers trained.
- Effectiveness checked, then the CAPA is closed with evidence.
In your work: an event closes on evidence, not on a promise. Attach the SOP version and training records.
Use this for your own events
The same five steps apply to any QES event, whether it starts in the field, on the production line or in an audit.
| Stage | Question | In this example | Moves on when |
|---|---|---|---|
| 1 · Report | What happened? | Two tickets: “cable issue” | Ticket raised with symptom, action and result |
| 2 · Triage | Pattern? Reportable? Likely type? | Tickets linked; not an adverse event; suspected type: deviation | Linked, reportability decided, type suspected |
| 3 · Investigate | How far? How risky? Why? | Risk assessment not required (documented); solder paste on USB-C; final-test gap | Risk decision recorded, root cause proven |
| 4 · Assign | Which path? Who owns it? | Type confirmed: deviation → CAPA with supplier, Factory, Production actions | Type confirmed, every action has an owner |
| 5 · Track & Outcome | Done? Did it work? | New sensors, new SOPs, flip test in training | Actions done, effective, evidence attached |
Worked example for training. Names, sites and ticket details are illustrative.